Are we on time? Sonja put in a fair amount of effort to document the project plan I had in my head. The following summary shows the planned schedule, updated as of March 2008.
| Start Date: | Thu 01/05/03 |
| Projected Finish Date: | Sun 06/03/11 |
| Name | Start | Finish | % Complete |
|---|---|---|---|
| Start Project | Thu 01/05/03 | 100% | |
| Planning | Thu 01/05/03 | Wed 28/05/03 | 100% |
| Design | Thu 29/05/03 | Sun 03/08/03 | 100% |
| Factory | Thu 19/06/03 | Wed 03/11/04 | 100% |
| Hull | Thu 04/11/04 | Sun 01/06/08 | 85% |
| Mechanical | Sat 07/04/08 | Sun 5/10/08 | 4% |
| Interior | Mon 6/10/08 | Sat 4/09/10 | 0% |
| Exterior | Sun 5/09/10 | Fri 21/1/11 | 0% |
| Launch | Sat 22/1/11 | Sun 6/3/11 | 0% |
| Project complete | Sun 6/3/11 | 0% |